equipment cost

job costing equipmentDetermining the cost-per-hour for each piece of equipment or machinery  that your company owns and uses on a job site is a great tool for understanding, and even eventually, recouping the actual cost of the machine itself.  Once you have this information, you can improve the accuracy of your bidding, book equipment and machinery costs in your accounting software, and even identify ways in which you can maximize expenditures throughout the year.

Equipment and machinery cost-per-hour rates are calculated by adding together three distinct pieces of information:

  1. What it costs to own or lease (acquisition cost-per-hour)
  2. What it costs to maintain (maintenance cost-per-hour)
  3. What it costs to run operate it (running time fuel consumption cost-per-hour)

1.  Calculating Acquisition cost-per-hour (ACPH)

Formula:  Divide the total price paid (including interest paid) by the projected number of lifetime hours.

Example:

21” rotary mower purchase price: $1,100.00
Interest none
Lifetime hours: 750 hours
(2.5 hours/day, 5 days week/30 weeks/year for 2 years)
Salvage value: none

Acquisition cost-per hour: $1,100.00 divided by 750 hours = $1.47 per hour

2.  Calculating Maintenance cost-per-hour (MCPH)

Formula:  Divide the estimated lifetime maintenance cost (repairs, parts, labor, blades, spark plugs, oil changes, filters, etc.) by the number of lifetime hours.

Example:

Lifetime maintenance cost:               $600.00

Maintenance cost per hour: $600.00 divided by 750 hours = $0.80 per hour

3.  Calculating Running-time Fuel Consumption cost-per-hour (RT/FC CPH)

Formula:  Determine how long one gallon of fuel lasts for the piece of machinery.  Divide the price per gallon of the fuel by the hours used each day.

Example:

Cost per gallon of fuel:                                    $2.50

Running-time fuel consumption cost-per-hour: $2.50 divided by 2.5 hours = $1.00 per hour

Total Cost-Per-Hour:$1.47  Acquisition cost-per-hour (ACPH)$0.80  Maintenance cost-per-hour (MCPH)

$1.00 Running-time Fuel consumption cost-per-hour (RT/FC CPH)

$3.27

Let’s look at another example, this time determining the cost-per hour for a compact tractor.

Purchase Price: $23,000.00
Interest: $ 5,520.00
Salvage Value: $ 8,000.00
Life Expectancy: 3,000 hours (300 hours per year for 10 years)
Lifetime Maintenance Cost: $18,000.00
Fuel Price: $2.50 per gallon
Fuel Used per hour: 1.5 gallons

Acquisition cost-per-hour (ACPH): ($23,000.00 + $5,520.00 – $8,000.00 = $20,520.00)

$20,520.00 divided by 3,000 hours = $6.84

Maintenance cost-per-hour (MCPH): $18,000.00 divided by 3,000 hours = $6.00

Running-time fuel cost-per-hour (RT/FC CPH): $2.50 divided by 1.5 hours = $1.67

Total Cost-Per-Hour: $6.84 + $6.00 + $1.67 = $14.51

Notes: Your dealer should have data regarding estimated lifetime maintenance cost and fuel consumption.  If you buy used equipment, cost it out using the “new” purchase price.  The total cost-per-hour is usually the same for new and used equipment, and useful life, repair and maintenance costs, are easier to determine for new equipment.  Using the new purchase price also automatically adjusts your rates for inflation and price increases.You can cost out leased machines using the same formulas and adjusting the life expectancy, lifetime maintenance and fuel price, to account for the shorter term.

To determine fuel cost, you can also fill up the tank and divide the fill-up price by the total running hours.

Even if you prefer to base your estimates on a per-labor-hour rate, the Cost-Per-Hour method prevents you from understating or overstating the actual equipment cost for the job being bid.

You can verify your Cost-Per-Hour figures in several ways:

  1. Compare your hourly rates to those of your local equipment rental company.  Reduce their rental rates by 40-50% to remove their markups.  Your rates should be reasonably close to theirs.
  2. Contact your local dealer to verify maintenance costs, production rates, fuel consumption, lifetime hours, etc.
  3. Contact your local Department of Transportation (DOT) office, they have manuals containing CPH data for maintenance, and will often share these figures with you for comparison purposes.

Ways in which you can reduce your Cost-Per-Hour figures:

  1. Take advantage of multi-unit discounts offered by some manufacturers.
  2. Check with your local dealer about new engine technologies.
  3. Use the CPH calculations to develop a better understanding of which piece(s) of equipment will lower your field operation costs over time.

You can also use the Equipment Cost-Per-Hour (ECPH) to develop a better understanding of which pieces of equipment, or brand, could actually lower your field operation costs over time.  By matching up the purchase price of several different pieces of machinery against long-term variables, such as annual maintenance cost and serviceability, production rates, fuel costs, etc., the ECPH will help you to confirm the truth of you get what you pay for.

Armed with the knowledge of equipment cost-per-hour, bring this into your accounting program and job costing.  This will help you to take the “guess-work” out of future bidding and increase your company’s bottom line.

_________________________________________________________________________

Realizing that these formulas are complex and time-consuming to perform; and the fact that given the current state of the economy, that it is extremely critical to be able to quickly and accurately, update these prices at a moment’s notice – we’ve developed an Excel spreadsheet that will allow you to quickly and easily update these figures.

Download our Equipment Cost Calculator at http://www.sunburstsoftwaresolutions.com/view-document-details/equipment-costs-calculator.htm.

QuickBooks equipment job costing instruction Once you know your Equipment Costs per hour, use QuickBooks to track these costs for job costing purposes by downloading our FREE 17-page eBook “Advanced Job Costing – Getting Equipment Costs into Job Costing” by clicking here.

Congratulations, you have just picked up your first construction client!

Every contractor should have a computer as part of his "toolbelt"As an Certified QuickBooks ProAdvisor, a “contractor” or a Bookkeeper/Office Manager has contacted you for a contractor because they need “help” with their QuickBooks file.  The chances are good that you have completed one of the various “New Client Interviews” that are readily available, you arrive at the contractor’s office, and start to review their current QuickBooks setup only to find:

  • A Chart of Accounts that is so long it could easily be considered a “book” OR one that is so short you wonder how they manage to keep accurate records.
  • An Item List that is so long that it too could be considered a “book” OR one that consists of only a few items.
  • A Payroll Item List that is so long that it too could be considered a “book” OR one that consists of only a few items

In the case of the Chart of Accounts, Item, and Payroll Item Lists feeling like “books” most ProAdvisors first thought is “oh what a mess, we need to clean this up!”

STOP!

This initial reaction may not be the best approach to dealing with a construction client, so let’s address some areas that most of the New Client Interviews I’ve ever seen – never take into consideration.  Also, remember that your construction clients in-house management reporting needs do not, and probably will not, perfectly line up with financial-statement or tax return reporting requirements.  However, you will find it worthwhile to help them retrieve the information that they desperately need – even if it means a bit more work from you or their Accountant on a periodic or year-end basis.

So, let’s talk about some of those questions that are not in the New Client Interviews, it is impossible to cover all of them, but you can certainly add these to your “list”:

  • Do you subcontract portions of your construction projects to other contractors?
  • How are you currently tracking these subcontracts?
  • Do you have a method of tracking your Subcontractor’s Worker’s Comp and/or General Liability Insurance Expiration Dates?
  • Do any of your construction contracts require that Retainage be held on current invoices and paid to you at a later date?
  • Will you be withholding Retainage on payments to your Subcontractors?
  • Will a standard QuickBooks Invoice or Progress Invoice be sufficient for billing purposes?  If not what type of billings do you need to submit?  Is this for all jobs or just some jobs?
  • Do you have any special job-costing needs, such as tracking equipment or trucks?
  • How are you doing your Estimates?  Using QuickBooks, Excel, a 3rd party Estimating program with Cost Books?
  • Are any of your construction projects funded with Federal, State or ARRA monies and require certified payroll reporting?  If so, how are you currently producing these reports?
  • How are you paying the fringe benefits associated with these Federal, State, or ARRA Funded Projects?  Are they paid to a Union or a bona-fide plan?
  • Are you required to submit Union Benefit and Union Dues Reports?  If so, how often?
  • Are you required to submit EEOC/Work Utilization Reports for these Federal, State, or ARRA funded projects?
  • Are all of your projects funded with Federal, State, or ARRA monies?  Or do you perform work on private jobs also?
  • Are your crews working locally with a foreman, supervisor or project manager submitting timesheets to the office?
  • Do your employees perform work under multiple work classifications and or pay rates throughout the week?
  • Are you required to pay overtime using weighted-average overtime calculations?
  • Do your projects frequently have Change Orders?  If so, how are you tracking these?
  • What tasks are you still doing manually or with an Excel spreadsheet?
  • What tasks are currently taking the most time?

As you can see these questions will help you to zero in on their needs and you can then help them set up a QuickBooks file that will be a “workhorse” instead of one that “underperforms” and causes frustration.

QuickBooks will not automatically provide some of the solutions to the needs of contractors, for example:  tracking Retainage, equipment costs, union or bona-fide plan fringe benefits – but properly setup QuickBooks “can be made” to do so; and of course, there are always third-party applications that will help with the “tough stuff”.

Now that you have some more information about the client’s needs – your first step should be to help them (and yourself) get organized by making a list of their needs!  However, before you begin implementing new procedures – you should review their current QuickBooks file to make sure it will provide them with the desired results.

Search…….

Loading

FREE 30-Day Trials

Request FREE 30-day Trials of QuickBooks add-ons for Certified Payroll, AIA Billing & Payroll Wage Management.
Free 30 day trials of QuickBooks integrated add-ons for certified payroll, aia billing and weighted-average overtime
February 2012
S M T W T F S
« Jan    
 1234
567891011
12131415161718
19202122232425
26272829  
Top 10 Blogger Award Toolbox for Finance